Wind Generation

11361.855 MW

Wind Installed Capacity

9331.365 MW

Wind Grid Connected State Transmission Utility

2030.49 MW

Central Transmission Utility

12,778 MU

Wind Generation


For STU Connections Application Process charges for wind (on time collection)

  • Evacuation Application Fee - 5 Lakhs/Application
  • Load Flow Study Charges - 1 Lakh upto 100MW & 1.5 Lakhs for above 100MW
  • Refundable security deposit for load flow study - 20 Lakhs/Application
  • WEG location registeration fee - 33300/Location
  • Consultancy Charges - 66600/Location
  • Non Refundable Infrastructure Development charges for connecting in TNPDCL,TANTRANSCO owner SS - 30 Lakhs/MW
  • Inspection,testing and commissioning charges - 10% estimate cost

Restructuring charges after commissioning of WEG (Every Month Collection)

  • Transmission Charges - 5580.26/MW/Day
  • Scheduling Charges - 200/Day
  • System operating charges - 92.46/MW/Day
  • Wheeling charges - 05. /Unit
  • O&M Charges - 3.017 Lakhs/MW

Wind Energy Passing Areas in Tamil Nadu

  • Aralvoimozhi Pass (Kanyakumari, Tirunelveli)
  • Kambam Pass (Theni, Dindigul)
  • Palghat Pass (Coimbatore)
  • Sengottah Pass (Tenkasi)
Save-energy1 Future-proof your wallet: Smart energy choices save money today and tomorrow  Save-energy2 Think Green, Drive Clean: Electric vehicles, the path to cleaner air.

 Save-energy1 Use electricity wisely, it's not magic, it's a resource  Save-energy3 Stars Align, Bills Decline - Use star rated appliances for a better future.   Save-energy4 Be a champion for Change - Every watt saved makes a difference. 

Explore Our Trusted Websites